29 MW generation in Doa Ana Cty, NM · In queue since July 2015 · Proposed COD November 2021
29 MW
Capacity
1
Components
Geothermal
10y 8m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
6y 4m
Schedule
54 months past proposed COD
Construction75%
Queue EntryJul 28, 2015
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2021-11-01
Project Details
State
NM
County
Doa Ana Cty
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Picacho Station
Data Source
LBNL