BetaActiveGeothermalPNMLBNL
29 MW generation in Dona Ana Cty, NM · In queue since March 2014 · Proposed COD March 2018
29 MW
Capacity
1
Components
Geothermal
12 years
In Queue
System Impact Study
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
4 years
Schedule
98 months past proposed COD
Impact Study25%
Queue EntryMar 26, 2014
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-03-01
Project Details
State
NM
County
Dona Ana Cty
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Picacho Station
Data Source
LBNL