— Project Summary

Queue ID
PNM-IA-PNM-2013-01
Capacity
42.3 MW
Technology
Gas
Status
active
Location
Valencia, NM
Region
West
Developer
IA Status
IA Executed

BetaActiveGasPNMLBNL

42.3 MW generation in Valencia, NM · In queue since May 2013 · Proposed COD July 2017

42.3 MW

Capacity

1

Components

Gas

12y 10m

In Queue

IA Executed

IA Status

COD target: 2017

Interconnection Timeline

Total Duration

4y 2m

Schedule

106 months past proposed COD

Construction75%
Queue EntryMay 21, 2013

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2017-07-01

Project Details

State

NM

County

Valencia

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

PNM-GPD La Luz Energy Center #2

Data Source

LBNL

No news available for this project.