BetaActiveSolarPNMLBNL
40 MW generation in Guadalupe Cty, NM · In queue since August 2012 · Proposed COD November 2016
40 MW
Capacity
1
Components
Solar
13y 7m
In Queue
IA Executed
IA Status
COD target: 2016
Interconnection Timeline
Total Duration
4y 3m
Schedule
114 months past proposed COD
Construction75%
Queue EntryAug 28, 2012
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2016-11-01
Project Details
State
NM
County
Guadalupe Cty
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Aragonne Mesa
Data Source
LBNL
No news available for this project.