BetaActiveSolarPJMLBNL + Live
86.38 MW generation in Caroline, VA · In queue since June 2023 · Proposed COD December 2029
86.38 MW
Capacity
1
Components
Solar
2y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 6m
In Study38%
Queue EntryJun 30, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-15
Project Details
State
VA
County
Caroline
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
St. Johns _x0013_ Woodpecker 115 kV
Data Source
LBNL + Live
No news available for this project.