BetaActiveSolarBatteryPJMLBNL + Live
800 MW hybrid in Clermont, OH · In queue since May 2023 · Proposed COD October 2028
800 MW
Capacity
1
Components
Solar
2y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 5m
In Study38%
Queue EntryMay 8, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-01
Project Details
State
OH
County
Clermont
Region
PJM
Developer
—
Utility
DEOK
Entity
PJM
Point of Interconnection
Zimmer 345 kV
Data Source
LBNL + Live
No news available for this project.