— Project Summary

Queue ID
PJM-AJ1-008
Capacity
800 MW
Technology
Solar+Battery
Status
active
Location
Clermont, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

800 MW hybrid in Clermont, OH · In queue since May 2023 · Proposed COD October 2028

800 MW

Capacity

1

Components

Solar

2y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 5m

In Study38%
Queue EntryMay 8, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-01

Project Details

State

OH

County

Clermont

Region

PJM

Developer

Utility

DEOK

Entity

PJM

Point of Interconnection

Zimmer 345 kV

Data Source

LBNL + Live

No news available for this project.