BetaActiveWindPJMLBNL + Live
133 MW generation in Champaign, OH · In queue since March 2023 · Proposed COD May 2021
133 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
3 years
Schedule
59 months past proposed COD
In Study38%
Queue EntryMar 10, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-05-31
Project Details
State
OH
County
Champaign
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
East Lima-Marysville 345kV
Data Source
LBNL + Live
No news available for this project.