BetaActiveWindPJMLBNL + Live
173 MW generation in Kankakee, IL · In queue since March 2023 · Proposed COD May 2026
173 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 2m
In Study38%
Queue EntryMar 10, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-01
Project Details
State
IL
County
Kankakee
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Wilton Center - Loretto 345 kV(CIR Increase)
Data Source
LBNL + Live
No news available for this project.