20 MW hybrid in Luzerne, PA · In queue since March 2023 · Proposed COD December 2027
20 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 9m
In Study38%
Queue EntryMar 10, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
PA
County
Luzerne
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Salem-Beacon Power 69 kV
Data Source
LBNL + Live
No news available for this project.