— Project Summary

Queue ID
PJM-AI2-434
Capacity
20 MW
Technology
Solar+Battery
Status
active
Location
Lycoming, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

20 MW hybrid in Lycoming, PA · In queue since March 2023 · Proposed COD December 2026

20 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 9m

In Study38%
Queue EntryMar 9, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

PA

County

Lycoming

Region

PJM

Developer

Utility

PPL

Entity

PJM

Data Source

LBNL + Live