BetaActiveOffshore WindPJMLBNL + Live
2,138.85 MW generation in Atlantic, NJ · In queue since March 2023 · Proposed COD February 2030
2,138.85 MW
Capacity
1
Components
Offshore Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 11m
In Study38%
Queue EntryMar 10, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-02-28
Project Details
State
NJ
County
Atlantic
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Larrabee Collector Station 230 kV
Data Source
LBNL + Live
No news available for this project.