BetaActiveWindPJMLBNL + Live
22.2 MW generation in Lee, IL · In queue since March 2023 · Proposed COD December 2025
22.2 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 9m
Schedule
3 months past proposed COD
In Study38%
Queue EntryMar 9, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
IL
County
Lee
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Mendota Hills 138 kV
Data Source
LBNL + Live
No news available for this project.