— Project Summary

Queue ID
PJM-AI2-401
Capacity
48 MW
Technology
Solar+Battery
Status
active
Location
White, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

48 MW hybrid in White, IN · In queue since March 2023 · Proposed COD December 2025

48 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 9m

Schedule

3 months past proposed COD

In Study38%
Queue EntryMar 2, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

IN

County

White

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Olive-Reynolds #1 345 kV

Data Source

LBNL + Live

No news available for this project.