BetaActiveSolarPJMLBNL + Live
19.5 MW generation in Ogle, IL · In queue since March 2023 · Proposed COD April 2026
19.5 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 1m
In Study38%
Queue EntryMar 4, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
IL
County
Ogle
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Twombley Road 138kV (CIR Increase)
Data Source
LBNL + Live
No news available for this project.