BetaActiveWindPJMLBNL + Live
77.87 MW generation in Logan, IL · In queue since March 2023 · Proposed COD April 2023
77.87 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1 month
Schedule
36 months past proposed COD
In Study38%
Queue EntryMar 4, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-04-17
Project Details
State
IL
County
Logan
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
TSS 994 345 kV (CIR Increase)
Data Source
LBNL + Live
No news available for this project.