— Project Summary

Queue ID
PJM-AI2-366
Capacity
93.6 MW
Technology
Solar
Status
active
Location
Van Wert, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

93.6 MW generation in Van Wert, OH · In queue since March 2023 · Proposed COD September 2024

93.6 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 6m

Schedule

18 months past proposed COD

In Study38%
Queue EntryMar 4, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-25

Project Details

State

OH

County

Van Wert

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Maddox Creek-RP Mone 345 kV

Data Source

LBNL + Live

No news available for this project.