— Project Summary

Queue ID
PJM-AI2-365
Capacity
32.06 MW
Technology
Solar
Status
active
Location
Preston, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

32.06 MW generation in Preston, WV · In queue since March 2023 · Proposed COD September 2021

32.06 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3 years

Schedule

55 months past proposed COD

In Study38%
Queue EntryMar 4, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-09-30

Project Details

State

WV

County

Preston

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Lake Lynn-Hazelton 138 kV II

Data Source

LBNL + Live

No news available for this project.