— Project Summary

Queue ID
PJM-AI2-356
Capacity
57.2 MW
Technology
Wind
Status
active
Location
Grant, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveWindPJMLBNL + Live

57.2 MW generation in Grant, WV · In queue since March 2023 · Proposed COD July 2027

57.2 MW

Capacity

1

Components

Wind

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntryMar 4, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-31

Project Details

State

WV

County

Grant

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Greenland Gap 500 kV II

Data Source

LBNL + Live

No news available for this project.