— Project Summary

Queue ID
PJM-AI2-354
Capacity
58.7 MW
Technology
Wind
Status
active
Location
Grant, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveWindPJMLBNL + Live

58.7 MW generation in Grant, WV · In queue since March 2023 · Proposed COD January 2026

58.7 MW

Capacity

1

Components

Wind

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 10m

Schedule

3 months past proposed COD

In Study38%
Queue EntryMar 3, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

Project Details

State

WV

County

Grant

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Williams 138 kV

Data Source

LBNL + Live

No news available for this project.