BetaActiveWindPJMLBNL + Live
16 MW generation in Allegany, MD · In queue since March 2023 · Proposed COD April 2024
16 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 1m
Schedule
24 months past proposed COD
In Study38%
Queue EntryMar 3, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-01
Project Details
State
MD
County
Allegany
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Carlos Jct. _x0013_ Ridgeley 138 kV
Data Source
LBNL + Live