BetaActiveOffshore WindPJMLBNL + Live
94.6 MW generation in Cape May, NJ · In queue since March 2023 · Proposed COD December 2024
94.6 MW
Capacity
1
Components
Offshore Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 9m
Schedule
15 months past proposed COD
In Study38%
Queue EntryMar 3, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
NJ
County
Cape May
Region
PJM
Developer
—
Utility
AEC
Entity
PJM
Point of Interconnection
BL England 138 kV
Data Source
LBNL + Live
No news available for this project.