— Project Summary

Queue ID
PJM-AI2-325
Capacity
178.7 MW
Technology
Offshore Wind
Status
active
Location
Ocean, NJ
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveOffshore WindPJMLBNL + Live

178.7 MW generation in Ocean, NJ · In queue since March 2023 · Proposed COD December 2024

178.7 MW

Capacity

1

Components

Offshore Wind

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 9m

Schedule

15 months past proposed COD

In Study38%
Queue EntryMar 3, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

NJ

County

Ocean

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Oyster Creek 230 kV

Data Source

LBNL + Live

No news available for this project.