— Project Summary

Queue ID
PJM-AI2-313
Capacity
17.1 MW
Technology
Solar
Status
active
Location
Meigs, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

17.1 MW generation in Meigs, OH · In queue since March 2023 · Proposed COD December 2023

17.1 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

9 months

Schedule

27 months past proposed COD

In Study38%
Queue EntryMar 2, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

OH

County

Meigs

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Ravenswood-Hemlock 69kV

Data Source

LBNL + Live

No news available for this project.