— Project Summary

Queue ID
PJM-AI2-303
Capacity
18.1 MW
Technology
Solar
Status
active
Location
Montgomery, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

18.1 MW generation in Montgomery, OH · In queue since March 2023 · Proposed COD December 2025

18.1 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 9m

Schedule

3 months past proposed COD

In Study38%
Queue EntryMar 3, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

OH

County

Montgomery

Region

PJM

Developer

Utility

Dayton

Entity

PJM

Point of Interconnection

Crown-New Lebanon 69 kV

Data Source

LBNL + Live

No news available for this project.