BetaActiveSolarPJMLBNL + Live
30.8 MW generation in Edgecombe, NC · In queue since March 2023 · Proposed COD December 2020
30.8 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3 years
Schedule
64 months past proposed COD
In Study38%
Queue EntryMar 3, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-11
Project Details
State
NC
County
Edgecombe
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Benson-Dunbar 115 kV
Data Source
LBNL + Live
No news available for this project.