BetaActiveSolarPJMLBNL + Live
42 MW generation in Franklin, PA · In queue since March 2023 · Proposed COD January 2028
42 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 10m
In Study38%
Queue EntryMar 3, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
PA
County
Franklin
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
McConnellsburg-Texas Eastern 138 kV
Data Source
LBNL + Live
No news available for this project.