BetaActiveSolarPJMLBNL + Live
45 MW generation in Hardin, OH · In queue since March 2023 · Proposed COD February 2023
45 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3 years
Schedule
38 months past proposed COD
In Study38%
Queue EntryMar 3, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-02-25
Project Details
State
OH
County
Hardin
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
East Lima-Marysville 345kV
Data Source
LBNL + Live
No news available for this project.