— Project Summary

Queue ID
PJM-AI2-241
Capacity
55.5 MW
Technology
Solar
Status
active
Location
Columbiana, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

55.5 MW generation in Columbiana, OH · In queue since March 2023 · Proposed COD June 2025

55.5 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 3m

Schedule

10 months past proposed COD

In Study38%
Queue EntryMar 2, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

OH

County

Columbiana

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Congress-Toronto 138 kV II

Data Source

LBNL + Live

No news available for this project.