BetaActiveWindPJMLBNL + Live
49.4 MW generation in Centre, PA · In queue since March 2023 · Proposed COD June 2023
49.4 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3 months
Schedule
34 months past proposed COD
In Study38%
Queue EntryMar 2, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
PA
County
Centre
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Eagle Valley 115kV II
Data Source
LBNL + Live
No news available for this project.