BetaActiveBatteryPJMLBNL + Live
240 MW storage in Mchenry, IL · In queue since March 2023 · Proposed COD November 2024
240 MW
Capacity
1
Components
Battery
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 8m
Schedule
17 months past proposed COD
In Study38%
Queue EntryMar 2, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-06
Project Details
State
IL
County
Mchenry
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Silver Lake 345
Data Source
LBNL + Live