BetaActiveWindPJMLBNL + Live
6.16 MW generation in Lasalle, IL · In queue since February 2023 · Proposed COD February 2023
6.16 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
<1 month
Schedule
37 months past proposed COD
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-02-28
Project Details
State
IL
County
Lasalle
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
LaSalle 138kV
Data Source
LBNL + Live
No news available for this project.