BetaActiveWindPJMLBNL + Live
97.5 MW generation in Mclean, IL · In queue since February 2023 · Proposed COD March 2023
97.5 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1 month
Schedule
37 months past proposed COD
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-03-17
Project Details
State
IL
County
Mclean
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Brokaw-Pontiac 345kV
Data Source
LBNL + Live
No news available for this project.