— Project Summary

Queue ID
PJM-AI2-172
Capacity
37.2 MW
Technology
Solar
Status
active
Location
Jay, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

37.2 MW generation in Jay, IN · In queue since February 2023 · Proposed COD December 2022

37.2 MW

Capacity

1

Components

Solar

3y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 1m

Schedule

39 months past proposed COD

In Study38%
Queue EntryFeb 28, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

IN

County

Jay

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Pennville - Adams 138 kV

Data Source

LBNL + Live

No news available for this project.