BetaActiveSolarPJMLBNL + Live
37.2 MW generation in Jay, IN · In queue since February 2023 · Proposed COD December 2022
37.2 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 1m
Schedule
39 months past proposed COD
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
IN
County
Jay
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Pennville - Adams 138 kV
Data Source
LBNL + Live
No news available for this project.