BetaActiveWindPJMLBNL + Live
78 MW generation in Fountain, IN · In queue since February 2023 · Proposed COD December 2024
78 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 10m
Schedule
15 months past proposed COD
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
IN
County
Fountain
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Dequine - Eugene 345 kV
Data Source
LBNL + Live