— Project Summary

Queue ID
PJM-AI2-141
Capacity
18.75 MW
Technology
Solar
Status
active
Location
Edgecombe, NC
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

18.75 MW generation in Edgecombe, NC · In queue since February 2023 · Proposed COD May 2023

18.75 MW

Capacity

1

Components

Solar

3y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3 months

Schedule

34 months past proposed COD

In Study38%
Queue EntryFeb 28, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-05-31

Project Details

State

NC

County

Edgecombe

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Heartsease DP - Mayo Dunbar 115kV

Data Source

LBNL + Live

No news available for this project.