BetaActiveSolarPJMLBNL + Live
18.75 MW generation in Edgecombe, NC · In queue since February 2023 · Proposed COD May 2023
18.75 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3 months
Schedule
34 months past proposed COD
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-31
Project Details
State
NC
County
Edgecombe
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Heartsease DP - Mayo Dunbar 115kV
Data Source
LBNL + Live