BetaActiveOffshore WindPJMLBNL + Live
1,675.59 MW generation in Monmouth, NJ · In queue since February 2023 · Proposed COD February 2030
1,675.59 MW
Capacity
1
Components
Offshore Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7 years
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-02-28
Project Details
State
NJ
County
Monmouth
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Larrabee 230 kV
Data Source
LBNL + Live
No news available for this project.