BetaActiveSolarPJMLBNL + Live
11.976 MW generation in Putnam, OH · In queue since February 2023 · Proposed COD June 2023
11.976 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4 months
Schedule
33 months past proposed COD
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-28
Project Details
State
OH
County
Putnam
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Continental 69 kV
Data Source
LBNL + Live
No news available for this project.