BetaActiveWindPJMLBNL + Live
106.4 MW generation in Randolph, IN · In queue since February 2023 · Proposed COD February 2023
106.4 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
<1 month
Schedule
37 months past proposed COD
In Study38%
Queue EntryFeb 28, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-02-27
Project Details
State
IN
County
Randolph
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Desoto-Tanners Creek #1 345kV
Data Source
LBNL + Live