BetaActiveWindPJMLBNL + Live
42.6 MW generation in Paulding, OH · In queue since March 2023 · Proposed COD February 2023
42.6 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3 years
Schedule
37 months past proposed COD
In Study38%
Queue EntryMar 1, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-02-27
Project Details
State
OH
County
Paulding
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Haviland - Milan 138kV
Data Source
LBNL + Live
No news available for this project.