— Project Summary

Queue ID
PJM-AI2-087
Capacity
42.5 MW
Technology
Wind
Status
active
Location
Potter, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveWindPJMLBNL + Live

42.5 MW generation in Potter, PA · In queue since February 2023 · Proposed COD March 2023

42.5 MW

Capacity

1

Components

Wind

3y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

1 month

Schedule

37 months past proposed COD

In Study38%
Queue EntryFeb 27, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-03-03

Project Details

State

PA

County

Potter

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Gold-Sabinsville 115kV III

Data Source

LBNL + Live

No news available for this project.