— Project Summary

Queue ID
PJM-AI2-072
Capacity
27.8 MW
Technology
Solar
Status
active
Location
Jefferson, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

27.8 MW generation in Jefferson, OH · In queue since February 2023 · Proposed COD May 2024

27.8 MW

Capacity

1

Components

Solar

3y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 3m

Schedule

23 months past proposed COD

In Study38%
Queue EntryFeb 24, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-15

Project Details

State

OH

County

Jefferson

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Steubenville 69 kV

Data Source

LBNL + Live

No news available for this project.