— Project Summary

Queue ID
PJM-AI2-071
Capacity
150 MW
Technology
Battery
Status
active
Location
Atlantic, NJ
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

150 MW storage in Atlantic, NJ · In queue since February 2023 · Proposed COD March 2027

150 MW

Capacity

1

Components

Battery

3y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 1m

In Study38%
Queue EntryFeb 24, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-01

Project Details

State

NJ

County

Atlantic

Region

PJM

Developer

Utility

AEC

Entity

PJM

Point of Interconnection

Dorothy - Lewis 138 kV

Data Source

LBNL + Live

No news available for this project.