250 MW storage in Monmouth, NJ · In queue since February 2023 · Proposed COD December 2026
250 MW
Capacity
1
Components
Battery
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 10m
In Study38%
Queue EntryFeb 24, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
NJ
County
Monmouth
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Larabee - Atlantic 230 kV
Data Source
LBNL + Live