BetaActiveSolarPJMLBNL + Live
20 MW generation in Lunenburg, VA · In queue since February 2023 · Proposed COD March 2027
20 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 1m
In Study38%
Queue EntryFeb 24, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
VA
County
Lunenburg
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Lunenburg-Nutbush 115 kV
Data Source
LBNL + Live