BetaActiveSolarPJMLBNL + Live
16.4 MW generation in Marion, KY · In queue since February 2023 · Proposed COD December 2024
16.4 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 10m
Schedule
16 months past proposed COD
In Study38%
Queue EntryFeb 23, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
KY
County
Marion
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Marion County 161 kV
Data Source
LBNL + Live