BetaActiveSolarPJMLBNL + Live
35.8 MW generation in Blackford, IN · In queue since February 2023 · Proposed COD January 2026
35.8 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 11m
Schedule
3 months past proposed COD
In Study38%
Queue EntryFeb 23, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-01