BetaActiveSolarPJMLBNL + Live
7.28 MW generation in Venango, PA · In queue since February 2023 · Proposed COD January 2025
7.28 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 11m
Schedule
15 months past proposed COD
In Study38%
Queue EntryFeb 23, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-14
Project Details
State
PA
County
Venango
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Clark Summit-Emlenton 34.5 kV
Data Source
LBNL + Live
No news available for this project.