BetaActiveSolarPJMLBNL + Live
3.78 MW generation in Erie, PA · In queue since February 2023 · Proposed COD February 2024
3.78 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1 year
Schedule
26 months past proposed COD
In Study38%
Queue EntryFeb 23, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-02-06
Project Details
State
PA
County
Erie
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Fairview East 34.5 kV
Data Source
LBNL + Live
No news available for this project.