— Project Summary

Queue ID
PJM-AI2-056
Capacity
3.78 MW
Technology
Solar
Status
active
Location
Erie, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

3.78 MW generation in Erie, PA · In queue since February 2023 · Proposed COD February 2024

3.78 MW

Capacity

1

Components

Solar

3y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1 year

Schedule

26 months past proposed COD

In Study38%
Queue EntryFeb 23, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-02-06

Project Details

State

PA

County

Erie

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Fairview East 34.5 kV

Data Source

LBNL + Live

No news available for this project.