BetaActiveWindPJMLBNL + Live
6.8 MW generation in Blair, PA · In queue since February 2023 · Proposed COD December 2010
6.8 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2010
Interconnection Timeline
Total Duration
3y 1m
Schedule
186 months past proposed COD
In Study38%
Queue EntryFeb 23, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2010-12-10
Project Details
State
PA
County
Blair
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Summit-West Fall 115kV II
Data Source
LBNL + Live
No news available for this project.