BetaActiveBatteryPJMLBNL + Live
70 MW storage in Ocean, NJ · In queue since February 2023 · Proposed COD June 2027
70 MW
Capacity
1
Components
Battery
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 4m
In Study38%
Queue EntryFeb 17, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
NJ
County
Ocean
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Lakewood 230 kV II
Data Source
LBNL + Live
No news available for this project.